How likely are we to actually hit the deadline?

If your duration estimate is uncertain, a deadline is a bet, not a promise. Find out the real probability you finish on time — and the day you should plan around if you want an 80% chance of being safe.

The work is expected to take about 48 days, and you finish within a 60-day deadline in about 91.9% of outcomes. To hold an 80% chance, plan the schedule around about 55 days, not 48.

Duration estimate & deadline

Results

Probability you finish on time91.9%
Deadline (days used)60
Days to finish you can expect to stay at or under (normal approximation)
ScenarioP50P80P90
Days to finish 48 d 55 d 59 d

P50 duration means 50% of outcomes finish in that time or less — budgeting the schedule at P50 is roughly a coin flip. Your on-time probability may or may not be enough for your client; decide what confidence you need.

Formula

P(finish ≤ deadline) = Φ((deadline − mean) / σ)

finish days at P = mean + z·σ,  with mean = (O + 4M + P)/6,  σ = (P − O)/6

Normal approximation: probabilities use a normal approximation to a Beta-PERT duration — a fast, honest single-estimate shortcut.

Continue with the whole project

Turn one duration into a connected schedule

Create tasks, connect their dependencies, and compare deadlines in Schedule Lab. Parallel work and tasks on the critical path affect completion differently.

A single duration cannot show which dependency controls the finish date. Calendar dates here use elapsed days, not a business-day calendar. All outputs remain conditional on the assumptions you enter.

Read next: How dependencies change deadline confidence · First-project guide · Choose another free calculator

A date is cheap to promise; knowing which date you can defend is the expertise. Recommended reading: How to Remain Valuable When Intelligence Becomes Cheap .