How likely are we to actually hit the deadline?

If your duration estimate is uncertain, a deadline is a bet, not a promise. Find out the real probability you finish on time — and the day you should plan around if you want an 80% chance of being safe.

The answer

The work is expected to take about 48 days, and you finish within a 60-day deadline in about 91.9% of outcomes. To hold an 80% chance, plan the schedule around about 55 days, not 48.

Duration estimate & deadline

Results

Probability you finish on time
91.9%
Deadline (days used)
60
Days to finish you can expect to stay at or under (normal approximation)
ScenarioP50P80P90
Days to finish 48 d 55 d 59 d

P50 of 48 days means 50% of outcomes finish in that time or less — budgeting the schedule at P50 is roughly a coin flip. An 91.9% on-time figure for a 60-day deadline may or may not be enough for your client; decide what confidence you need.

Formula

P(finish ≤ deadline) = Φ((deadline − mean) / σ)

finish days at P = mean + z·σ,  with mean = (O + 4M + P)/6,  σ = (P − O)/6

Normal approximation: probabilities use a normal approximation to a Beta-PERT duration — a fast, honest single-estimate shortcut.

Related tools

A single duration misses how tasks and dependencies really chain together. For a delivery date you can stand behind across the whole project, run the full app or read the methodology.