How likely are we to actually hit the deadline?
If your duration estimate is uncertain, a deadline is a bet, not a promise. Find out the real probability you finish on time — and the day you should plan around if you want an 80% chance of being safe.
The work is expected to take about 48 days, and you finish within a 60-day deadline in about 91.9% of outcomes. To hold an 80% chance, plan the schedule around about 55 days, not 48.
Duration estimate & deadline
Results
| Scenario | P50 | P80 | P90 |
|---|---|---|---|
| Days to finish | 48 d | 55 d | 59 d |
P50 duration means 50% of outcomes finish in that time or less — budgeting the schedule at P50 is roughly a coin flip. Your on-time probability may or may not be enough for your client; decide what confidence you need.
Formula
P(finish ≤ deadline) = Φ((deadline − mean) / σ)
finish days at P = mean + z·σ, with mean = (O + 4M + P)/6, σ = (P − O)/6
Normal approximation: probabilities use a normal approximation to a Beta-PERT duration — a fast, honest single-estimate shortcut.
Test an alternative
What changes if…?
Keep these results, then adjust an estimate above to compare. Your baseline stays in this tab until you clear it or reload. Values are rounded for display.
| Result | Baseline | Current |
|---|
No baseline yet. Keep a result you would like to compare.