Free tool / Schedule

Project capacity calculator

Check whether the available people-hours can cover the estimated work. Separate effort from elapsed time before making a delivery promise.

No signup. Calculations stay in this browser. Default values are illustrative, not market benchmarks.

Your assumptions

A whole number of people assumed interchangeable for this arithmetic check.
Working days, not elapsed calendar days.
Before applying the project availability percentage.
Remove meetings, other projects and non-project work.
Total hands-on effort across all people.

Results

Available project hours
336.0
Hours shortfall
64.0
Whole people needed at this availability
4
Resource-only working days needed
23.8
Required effort / available capacity
119.0%

Calculation

capacity = people × working days × hours/day × availability; working days needed = effort ÷ (people × hours/day × availability)

Amounts and percentages are rounded for display. These are deterministic checks for your assumptions, not guarantees.

Worked example: three people do not provide 480 project hours

Three people over 20 working days at eight hours per day provide 480 nominal hours. At 70% availability, only 336 belong to this project. An estimated 400 hours therefore leaves a 64-hour shortfall. With the same assumptions, you need four whole people or about 23.8 working days.

This is a capacity floor, not a schedule forecast

The calculation assumes divisible work, interchangeable people and constant availability. A task waiting on a client, a specialist bottleneck or a dependency chain can make elapsed delivery much longer. Adding a person does not automatically divide duration. Read effort versus duration and task dependencies before turning the result into a date.

Check the constrained skill as well as the whole team

Run a second check for the designer, reviewer or integration specialist whose work cannot be reassigned. Keep a baseline and reduce availability to see the effect of another commitment. The software estimating guide explains how to combine this capacity check with task dependencies and a deadline confidence check.

Frequently asked questions

Are the calculated days business days?

They are working days under your hours and availability assumptions. The tool does not apply a calendar, weekends, holidays or leave dates.

Can I promise the calculated duration?

It is only a resource arithmetic check. Dependencies, skill constraints, waiting time, uncertainty and coordination can require more elapsed time.