Free tool / Scope

Scope creep & change fee calculator

Put a cost on the additional work and a price on an approved change. See what happens to the original project margin if you absorb it without charging.

No signup. Calculations stay in this browser. Default values are illustrative, not market benchmarks.

Your assumptions

The agreed revenue before this additional work.
Exclude the new change from this number.
Include implementation, review, coordination and testing.
An internal cost rate, not the client billing rate.
Subcontractors, purchases or other costs not in the hourly rate.
Applies to the incremental work, not automatically to the whole project.
A label only. No exchange-rate conversion.

Results

Cost of additional work
3,500 USD
Change fee for target margin
4,667 USD
Project profit if change is absorbed
2,500 USD
Project margin if change is absorbed
10.4%
Original price plus change fee
28,667 USD

Calculation

additional cost = hours × loaded cost/hour + direct expenses; change fee = additional cost ÷ (1 − target margin)

Amounts and percentages are rounded for display. These are deterministic checks for your assumptions, not guarantees.

Worked example: an unpaid change more than halves profit

A 24,000 project with 18,000 cost starts with 6,000 gross profit. Another 40 hours at 75 per hour plus 500 of expenses costs 3,500. Absorbing it leaves 2,500 profit and a 10.4% project margin. A 25% margin on the change requires a fee of 4,666.67.

Define the change before assigning a fee

Write down the added deliverable, acceptance criteria, rework to existing tasks, extra reviews and effects on the delivery date. A deterministic hours estimate does not describe uncertainty in those items. For uncertain work, use a three-point bid-price check or model the revised project in the licensed app.

Keep incremental and project economics separate

The change fee reaches the target margin on the added cost only. An underpriced original project can remain underpriced after a properly priced change. Read the unbilled-hours example and the uncertainty-aware change-request guide, then use the proposal checklist to document the agreed scope.

Frequently asked questions

Should I enter a billing rate or a cost rate?

Enter the loaded cost of doing the work. The calculator then adds the target margin to calculate a selling fee. Using a billing rate can count profit twice.

Does a change fee automatically preserve the project margin?

No. The fee preserves the chosen margin on the incremental cost. The original price and original cost still determine the economics of the original scope.