Risk mitigation value calculator

Compare one discrete risk before and after a proposed action. Keep the remaining risk and the cost of the action visible instead of treating mitigation as free.

No signup. Calculations stay in this browser. Default values are illustrative, not market benchmarks.

Your assumptions

Your assessed chance of this named event.
A single conditional severity; include costs caused by any delay.
The remaining event probability if the action is completed.
The action may reduce severity as well as probability.
Include the time and expenses required to perform it.
A label only. No exchange-rate conversion.

Results

Expected risk cost before
3,600 USD
Expected residual risk cost
800 USD
Action plus expected residual risk
2,300 USD
Net expected benefit
1,300 USD
Break-even action cost
2,800 USD

Calculation

expected risk cost = probability × impact; net benefit = expected cost before − expected residual cost − action cost

Amounts and percentages are rounded for display. These are deterministic checks for your assumptions, not guarantees.

Worked example: spend 1,500 to reduce expected cost by 2,800

A 30% chance of a 12,000 event gives an expected cost of 3,600. If a 1,500 action reduces the chance to 10% and the impact to 8,000, residual expected cost is 800. Action plus residual expectation is 2,300, so net expected benefit is 1,300. The break-even action spend is 2,800.

Expected value is not a confidence reserve

In the simplified original model, the event costs either zero or 12,000, not 3,600 in each project. An average can compare actions, but cannot tell you the cash needed in the event branch or the probability that a quote protects a margin. Read the mitigation decision walkthrough and contingency without double-counting.

Test the residual assumption

Record why the action changes probability or severity, who will perform it and what evidence would confirm completion. Try a weaker effect as a second scenario. For multiple risks, dependencies or uncertain severities, use the full project model. This tool assumes a single event and a certain action cost; it does not measure safety, reputation or other non-monetary consequences.

Frequently asked questions

What does a negative break-even action cost mean?

The entered residual expected risk cost exceeds the original expected risk cost. Even a free action would worsen expected monetary cost under those assumptions.

Does positive expected benefit guarantee a saving?

No. Expected values average across modeled outcomes. One project can still incur the mitigation cost and the residual event.