Price a risk register, not its average

Four discrete risks add up to a $7,050 expected cost. The outcome is never $7,050. A worked example shows what to price instead of the average.

A risk register is a list of lumpy outcomes

A task range describes ordinary variation: it takes a bit longer or a bit shorter. A risk event is different. It either happens or it does not, and when it does it adds a block of cost. The usual way to price a register is to multiply probability by impact for each line and add the results. That figure is a legitimate average, but it is not what the project will cost.

Four risks, worked through

Assume four independent, illustrative risks on a fixed-price delivery:

Illustrative risk register
RiskProbabilityAdded cost if it happensProbability × impact
Client content arrives late30%$6,000$1,800
Third-party API changes20%$12,000$2,400
Key person unavailable15%$9,000$1,350
Security review forces rework10%$15,000$1,500

The expected added cost is $1,800 + $2,400 + $1,350 + $1,500 = $7,050. Now enumerate every combination of the four events. The chance that none of them happens is 0.70 × 0.80 × 0.85 × 0.90, or about 42.8%. In that world the risk cost is $0. The most common non-zero outcome, the client delay alone, has a probability of 18.4%. A risk cost of exactly $7,050 is not one of the possible outcomes.

Cumulative distribution of total risk cost (all 16 combinations)
Risk cost at or belowProbability
$042.8%
$6,00061.2%
$9,00068.8%
$12,00079.5%
$15,00087.5%
$21,00096.0%

What to read from it

Keep the register honest

Probabilities in a register are judgments, not measurements. Write the reason beside each one, check them against jobs you have actually finished, and revisit them when scope changes. Independence is also an assumption: two risks driven by the same client are not independent, and treating them as if they were understates the chance of several hitting at once.

Keep risk events out of your task ranges so the same delay is not priced twice; contingency without double counting shows how. Then check the resulting quote's loss probability with the fixed-price project calculator.